Potter Road Reconstruction- One lane open in each direction
Potter Road is now open with one lane in each direction (Northbound and Southbound). This will continue until spring when the third phase of construction is scheduled to start. The tentative completion for this project is Summer 2010.
2009 CIP – Contract C – Project Complete
The 2009 CIP Contract C project has been substantially completed. Note that miscellaneous items of work and site clean-up may continue for a few weeks.
Recently placed sod will be evaluated in the spring for acceptance. Any areas that do not grow or experience settlement (only as a result of the contract work) will be repaired.
If you have questions or concerns please contact Becka Shipp at the City of Des Plaines, Public Works and Engineering Department at 847-391-5388.
2009 CIP – Contract C – Schedule Update
Asphalt surface paving schedule announced:
11/18 – Complete full depth patching at curb line, prepare trench edges for surface
11/19 – Prepare trench edges for surface, begin surface paving
(Place leaves in parkway for leaf pick-up)
11/20 – Complete surface paving
ALL WORK IS WEATHER PERMITTING
Note that miscellaneous items of work and clean-up will continue for a few weeks. The project will be suspended over the winter months, and some work including landscaping will resume in the spring.
2009 CIP – Contract C – Schedule Update
Work anticipated for week of 11/13 to 11/20:
-Continue placing and grading topsoil, and placing sod
-Complete paving base pavement on miscellaneous areas on all streets
-Begin paving asphalt surface
ALL WORK IS WEATHER PERMITTING
Sod acceptance note: Sod will be accepted after 30 days if it is in healthy condition and growing. Due to placement so late in the season, the City will inspect the sod in the spring of next year. You will receive a letter of acceptance after which it is the homeowner’s responsibility to maintain the sod.
2009 CIP – Contract C – Schedule Update
Work anticipated for week of 11/6 to 11/13:
-Complete paving base pavement on miscellaneous areas on all streets
-Complete sewer manhole adjustments in roadway on all streets
-Continue backfilling and cleanup of jobsite
-Continue placing and grading topsoil, and placing sod
-Begin paving asphalt surface
ALL WORK IS WEATHER PERMITTING
Sod acceptance note: Sod will be accepted after 30 days if it is in healthy condition and growing. Due to placement so late in the season, the City will inspect the sod in the spring of next year. You will receive a letter of acceptance after which it is the homeowner’s responsibility to maintain the sod.
2009 CIP – Contract C Schedule Update
Work anticipated for week of 10/30 to 11/6:
-Continue paving base pavement on miscellaneous areas on all streets
-Begin sewer manhole adjustments in roadway on all streets
-Continue backfilling and cleanup of jobsite
-Continue placing and grading topsoil
Other anticipated work:
-Paving of asphalt surface
-Sod restoration
ALL WORK IS WEATHER PERMITTING
Potter Road Concrete Pavement Construction
The new pavement for Potter Road is currently being poured. These new lanes are tentatively scheduled to be opened to 2-Way traffic (one lane in each direction) by late November-early December. Per IDOT standard, some sawcutting of the pavement may take place within 24 hours of the pavement being poured. This is to prevent cracking of the new 12″ thick concrete pavement. Some of this sawcutting may occur overnight due to the IDOT requirement for the pavement to be sawcut within a 24 hour period.
2009 CIP – Contract C Schedule Update
Work for 10/29:
Contractor will resume paving the base course on all streets. Please do not park over the stone trench areas.
2009 CIP – Contract C Schedule Update
Anticipated work for 10/26 through 10/30:
- Continue concrete work on South Warrington, South Meyer, South Cumberland and Davis
- Continue miscellaneous backfilling and site clean-up
Other Anticipated Work
- Asphalt pavement restoration (postponed due to the inclement weather)
LEAF PICK-UP WILL BE ON WEDNESDAY, OCTOBER 28. PLEASE PLACE LEAVES IN THE PARKWAYS.
2009 Contract C – Schedule Update
Pavement restoration will begin on Thursday, October 22 in the following sequence:
1. Westgate Road
2. South Cumberland (Davis to North)
3. North Cumberland (to Warrington)
4. North Meyer
5. North Warrington
-Only the base course will be placed at this time (areas will be left low for final surface to be placed at a later date). Some smaller trench or patch areas may not be completed during this phase.
-Driveway aprons that were constructed on Tuesday 10/20 will remain CLOSED until test results are returned.
-Do not park on the street in the areas of work. Parking is allowed on Davis, Fletcher, Meyer (south of work limit) and Warrington (North of Cumberland or south of work limit).
-Pavement patching may continue on the south portion (including Davis, South Meyer and South Warrington) beginning as early as 10/23.
Other Anticipated Work for 10-19 through 10-23:
-Concrete work on Davis, South Meyer and South Warrington